Opens in a new tab

Breaking news

Greek Energy Minister To Disclose CINEA Letter In €67 Million Royal Terminal Funding Dispute

Minister Poised To Reveal Key Documents

Greek Energy Minister George Papanastasiou has indicated that he is prepared to publicly release the letter from CINEA (European Climate, Infrastructure and Environment Executive Agency) if necessary. The document in question concerns the retraction of €67 million from European funds allocated to the Royal terminal project. For further context on the Royal terminal, please refer to the Royal terminal developments.

Budget Discussions And Parliamentary Scrutiny

During a heated discussion in the parliamentary Budget Committee of the Ministry of Finance, Minister Papanastasiou addressed allegations made by Democratic Rally MP Kyriakos Chatziaganni. The MP had claimed government responsibility for the request to return the funds to the European Union, citing mismanagement. The minister refuted these claims, stating that not a single subsidy was lost but rather misallocated due to poor implementation. He affirmed, “If necessary, I will make the CINEA letter public,” emphasizing a commitment to accountability and transparency.

Financial Implications And Broader Impact

Beyond the contested €67 million, the minister underscored that the ramifications of the mismanagement extend further, noting that the Republic was set to secure €101 million from the European Union. This disclosure points to a larger financial and strategic impact on both national policy and the broader commitments to EU funding processes.

Commitment To A Transparent And Corrective Process

Minister Papanastasiou maintained that the government’s actions regarding the terminal project have been entirely transparent. He highlighted that plans for revising the project will only commence once a detailed study on the deviations between the existing constructions and the proposed design is completed. He stressed, “The project was undertaken with burdens, and now it must be systematically addressed.” In response, critics like MP Chatziaganni have urged the minister to abandon claims of non-responsibility and to implement the necessary corrections, including timely reporting to the EU.

Looking Ahead

As the investigation into the discrepancies continues, industry observers and policymakers alike are watching closely. The forthcoming study is expected to determine significant changes in the planning and execution of the project, with potential wide-ranging implications for governmental accountability and EU funding strategies.

Limassol Port Electrification Awaits Grid Connection And EU Funding

Plans to equip Limassol port with shore-side electricity are advancing at the technical level, but unresolved administrative procedures, a pending grid connection and the need to secure European funding continue to delay implementation.

The proposed shore-power system, also known as cold ironing, would allow vessels to connect to electricity while berthed, reducing reliance on onboard engines and cutting emissions and noise in the surrounding area.

Technical Studies Near Completion

Transport Minister Evi Tsolaki said work is progressing through the EU-backed DecarbonLim programme, which is preparing the technical assessment and feasibility study required before construction can begin. The ministry is seeking regular updates from the Cyprus Ports Authority on the studies’ completion timetable.

The initiative also involves Frederick University, Eurogate Container Terminal Limassol, DP World Limassol, the Electricity Authority of Cyprus, the Cyprus Transmission System Operator and Limassol Municipality.

Grid Connection Remains A Key Hurdle

Despite progress on the studies, construction cannot proceed until the project secures a connection to the national transmission network.

Tsolaki said the ministry has requested land from the Department of Lands and Surveys for an electricity substation. Once the site is allocated, the relevant applications can be submitted to the Cyprus Transmission System Operator to advance the grid-connection process.

Until these steps are completed, the project will remain in the preparatory phase, even if the technical studies are finalised.

European Funding Adds Urgency

The feasibility work under DecarbonLim will support an application for construction financing, Tsolaki said. A competitive European funding call is currently open, and the ministry intends to submit an application within the required timeframe.

The funding window has raised concerns in parliament. MP Fotini Tsiridou warned that further delays could undermine Cyprus’ chances of securing EU support, noting that similar port electrification projects elsewhere in the bloc have already received funding.

Speaking to Entrepreneurial Limassol, published by the Limassol Chamber of Commerce and Industry, Tsiridou said she had observed some progress but had yet to receive a formal response to her parliamentary question.

Environmental And Commercial Benefits

Tsiridou argued that shore-side electricity would deliver benefits beyond emissions reductions, including less noise and air pollution for residents near the port.

“Our port should not be disconnected from the rest of the city,” she said, describing shore-power infrastructure as both a necessity and a European obligation.

Across Europe, port electrification is increasingly linked to environmental performance and competitiveness. By allowing compatible vessels to switch off auxiliary engines while docked, shore-power systems can reduce local emissions and noise while supporting wider decarbonisation goals.

Construction Timetable Still Unclear

The Cyprus Ports Authority signed a contract with DBA S.p.A. in July 2025 for a comprehensive study of the system’s technical, economic and environmental requirements. The work was intended to establish the basis for installation and identify any necessary port infrastructure upgrades.

More than a year later, key steps concerning land allocation, grid connection and financing remain unresolved. No timetable has been announced for completing these procedures or submitting the final funding application.

Limassol’s shore-power project therefore remains between planning and implementation. Its next milestones are securing the substation site, progressing the transmission-network application and obtaining construction financing. Until these are in place, the port’s transition to shore-side electricity cannot move into the construction phase.

eCredo
The Future Forbes Realty Global Properties
Aretilaw firm
Uol

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter