Opens in a new tab

Breaking news

Greek Energy Minister Praises Authority’s Achievements And Charts A Strategic Path Forward

Energy, Commerce And Industry Minister George Papanastasiou recently expressed his satisfaction with the progress and accomplishments of the Hellenic Electric Authority (often referred to as ΑΗΚ) for 2024 during a visit to its headquarters on November 17, 2025. In a commendatory address, the Minister thanked management and staff for their cooperative efforts and underscored the Authority’s essential role in maintaining a secure energy system, ensuring reliable power supply, and working to lower electricity costs.

Key Infrastructure Upgrades And Market Innovations

The Minister highlighted several critical priorities that lie ahead. Notable among these are the comprehensive upgrading of transmission networks, the installation of advanced storage systems, and the execution of a development program focused on energy production. He also stressed the importance of fostering a competitive electricity market through measures such as the recent introduction of a new Technical Guide for zero-injection photovoltaic systems and the launch of pilot projects aimed at optimizing smart meter utilization to reduce costs.

Energy Authority Headquarters

Leveraging European Investment For A Modernized Grid

A fundamental element of this strategic roadmap involves the deployment of 120 million euros in European funds dedicated to the digitization and modernization of the transmission and distribution networks. This initiative is expected to mitigate renewable energy curtailments while ensuring more efficient system operations. In tandem, progress on smart meter installations continues apace, with full implementation scheduled by January 2027.

Enhancing Flexibility And Resilience In A Competitive Environment

The Minister further emphasized that by 2027, the Authority is tasked with implementing new tariff structures designed to more accurately reflect production profiles and varying demand peaks. Flexible interconnections and seamless integration of demand response mechanisms are set to become cornerstones of this evolving strategy. The launch of a competitive electricity market on September 15, 2025, marked a significant step forward following years of delays, with substantial support from the Distribution System Operator and other stakeholders.

Modernized Energy Infrastructure

Advancements In Production And Storage Capacity

On the production front, ongoing projects include the upgrade of the Dekeleia Power Station with new generators and an 80 MW storage system slated for operation by 2026. Looking further ahead, plans envisage a comprehensive 600 MW storage capability by 2030, complemented by a distributed 120 MW system with transparent participation rules by 2026. In parallel, the modernization of the Vasiliko power plant is underway, featuring a new natural gas unit and upgrades to existing infrastructure.

Energy Production Facility

Commitment To Operational Excellence And Resilience

As the Authority adapts to a competitive market landscape, Minister Papanastasiou reiterated the need to enhance operational flexibility, improve efficiency, and better serve the public. He concluded his address by expressing gratitude to the Authority’s personnel for their swift and effective response in restoring the electrical system following the severe fire incident in the mountainous region of Limassol in July 2025, a testament to the team’s professionalism and dedication.

Limassol Port Electrification Awaits Grid Connection And EU Funding

Plans to equip Limassol port with shore-side electricity are advancing at the technical level, but unresolved administrative procedures, a pending grid connection and the need to secure European funding continue to delay implementation.

The proposed shore-power system, also known as cold ironing, would allow vessels to connect to electricity while berthed, reducing reliance on onboard engines and cutting emissions and noise in the surrounding area.

Technical Studies Near Completion

Transport Minister Evi Tsolaki said work is progressing through the EU-backed DecarbonLim programme, which is preparing the technical assessment and feasibility study required before construction can begin. The ministry is seeking regular updates from the Cyprus Ports Authority on the studies’ completion timetable.

The initiative also involves Frederick University, Eurogate Container Terminal Limassol, DP World Limassol, the Electricity Authority of Cyprus, the Cyprus Transmission System Operator and Limassol Municipality.

Grid Connection Remains A Key Hurdle

Despite progress on the studies, construction cannot proceed until the project secures a connection to the national transmission network.

Tsolaki said the ministry has requested land from the Department of Lands and Surveys for an electricity substation. Once the site is allocated, the relevant applications can be submitted to the Cyprus Transmission System Operator to advance the grid-connection process.

Until these steps are completed, the project will remain in the preparatory phase, even if the technical studies are finalised.

European Funding Adds Urgency

The feasibility work under DecarbonLim will support an application for construction financing, Tsolaki said. A competitive European funding call is currently open, and the ministry intends to submit an application within the required timeframe.

The funding window has raised concerns in parliament. MP Fotini Tsiridou warned that further delays could undermine Cyprus’ chances of securing EU support, noting that similar port electrification projects elsewhere in the bloc have already received funding.

Speaking to Entrepreneurial Limassol, published by the Limassol Chamber of Commerce and Industry, Tsiridou said she had observed some progress but had yet to receive a formal response to her parliamentary question.

Environmental And Commercial Benefits

Tsiridou argued that shore-side electricity would deliver benefits beyond emissions reductions, including less noise and air pollution for residents near the port.

“Our port should not be disconnected from the rest of the city,” she said, describing shore-power infrastructure as both a necessity and a European obligation.

Across Europe, port electrification is increasingly linked to environmental performance and competitiveness. By allowing compatible vessels to switch off auxiliary engines while docked, shore-power systems can reduce local emissions and noise while supporting wider decarbonisation goals.

Construction Timetable Still Unclear

The Cyprus Ports Authority signed a contract with DBA S.p.A. in July 2025 for a comprehensive study of the system’s technical, economic and environmental requirements. The work was intended to establish the basis for installation and identify any necessary port infrastructure upgrades.

More than a year later, key steps concerning land allocation, grid connection and financing remain unresolved. No timetable has been announced for completing these procedures or submitting the final funding application.

Limassol’s shore-power project therefore remains between planning and implementation. Its next milestones are securing the substation site, progressing the transmission-network application and obtaining construction financing. Until these are in place, the port’s transition to shore-side electricity cannot move into the construction phase.

eCredo
The Future Forbes Realty Global Properties
Aretilaw firm
Uol

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter