Opens in a new tab

Breaking news

Cyprus Faces Energy Strain As Cold Wave Hits: Authorities Call For Power Conservation

A cold wave sweeping across Cyprus threatens to test the island’s energy infrastructure in the coming days. Chará Kousiappa, spokesperson for the Cyprus Transmission System Operator (TSOC), warned that the country could face serious challenges as energy demand surges.

“It will be a tough situation,” Kousiappa told the Cyprus News Agency. “We’re already seeing very high demand, and we’re continuously assessing the situation. We hope things will go smoothly, but we’re ready to act if necessary.”

The cold front is expected to hit shortly, with the most critical period for electricity demand falling between 6:00 PM and 9:00 PM—when renewable energy production drops off. During these peak hours, the power supply will be under significant pressure, as several key power units are offline due to scheduled maintenance or technical issues.

TSOC is closely monitoring the situation, and Kousiappa hopes that some of the power units currently under repair at the Dhekelia and Vasilikos stations can be brought back online before temperatures fall. She also emphasized the importance of energy conservation, urging the public to reduce electricity usage during peak hours and shift high-energy tasks, like laundry and dishwashing, to the day when solar power is at its peak.

As Cyprus braces for a difficult few days, authorities are calling on citizens to play their part in ensuring the stability of the island’s power grid.

Limassol Port Electrification Awaits Grid Connection And EU Funding

Plans to equip Limassol port with shore-side electricity are advancing at the technical level, but unresolved administrative procedures, a pending grid connection and the need to secure European funding continue to delay implementation.

The proposed shore-power system, also known as cold ironing, would allow vessels to connect to electricity while berthed, reducing reliance on onboard engines and cutting emissions and noise in the surrounding area.

Technical Studies Near Completion

Transport Minister Evi Tsolaki said work is progressing through the EU-backed DecarbonLim programme, which is preparing the technical assessment and feasibility study required before construction can begin. The ministry is seeking regular updates from the Cyprus Ports Authority on the studies’ completion timetable.

The initiative also involves Frederick University, Eurogate Container Terminal Limassol, DP World Limassol, the Electricity Authority of Cyprus, the Cyprus Transmission System Operator and Limassol Municipality.

Grid Connection Remains A Key Hurdle

Despite progress on the studies, construction cannot proceed until the project secures a connection to the national transmission network.

Tsolaki said the ministry has requested land from the Department of Lands and Surveys for an electricity substation. Once the site is allocated, the relevant applications can be submitted to the Cyprus Transmission System Operator to advance the grid-connection process.

Until these steps are completed, the project will remain in the preparatory phase, even if the technical studies are finalised.

European Funding Adds Urgency

The feasibility work under DecarbonLim will support an application for construction financing, Tsolaki said. A competitive European funding call is currently open, and the ministry intends to submit an application within the required timeframe.

The funding window has raised concerns in parliament. MP Fotini Tsiridou warned that further delays could undermine Cyprus’ chances of securing EU support, noting that similar port electrification projects elsewhere in the bloc have already received funding.

Speaking to Entrepreneurial Limassol, published by the Limassol Chamber of Commerce and Industry, Tsiridou said she had observed some progress but had yet to receive a formal response to her parliamentary question.

Environmental And Commercial Benefits

Tsiridou argued that shore-side electricity would deliver benefits beyond emissions reductions, including less noise and air pollution for residents near the port.

“Our port should not be disconnected from the rest of the city,” she said, describing shore-power infrastructure as both a necessity and a European obligation.

Across Europe, port electrification is increasingly linked to environmental performance and competitiveness. By allowing compatible vessels to switch off auxiliary engines while docked, shore-power systems can reduce local emissions and noise while supporting wider decarbonisation goals.

Construction Timetable Still Unclear

The Cyprus Ports Authority signed a contract with DBA S.p.A. in July 2025 for a comprehensive study of the system’s technical, economic and environmental requirements. The work was intended to establish the basis for installation and identify any necessary port infrastructure upgrades.

More than a year later, key steps concerning land allocation, grid connection and financing remain unresolved. No timetable has been announced for completing these procedures or submitting the final funding application.

Limassol’s shore-power project therefore remains between planning and implementation. Its next milestones are securing the substation site, progressing the transmission-network application and obtaining construction financing. Until these are in place, the port’s transition to shore-side electricity cannot move into the construction phase.

The Future Forbes Realty Global Properties
eCredo
Aretilaw firm
Uol

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter