Opens in a new tab

Breaking news

Cyprus Faces Energy Strain As Cold Wave Hits: Authorities Call For Power Conservation

A cold wave sweeping across Cyprus threatens to test the island’s energy infrastructure in the coming days. Chará Kousiappa, spokesperson for the Cyprus Transmission System Operator (TSOC), warned that the country could face serious challenges as energy demand surges.

“It will be a tough situation,” Kousiappa told the Cyprus News Agency. “We’re already seeing very high demand, and we’re continuously assessing the situation. We hope things will go smoothly, but we’re ready to act if necessary.”

The cold front is expected to hit shortly, with the most critical period for electricity demand falling between 6:00 PM and 9:00 PM—when renewable energy production drops off. During these peak hours, the power supply will be under significant pressure, as several key power units are offline due to scheduled maintenance or technical issues.

TSOC is closely monitoring the situation, and Kousiappa hopes that some of the power units currently under repair at the Dhekelia and Vasilikos stations can be brought back online before temperatures fall. She also emphasized the importance of energy conservation, urging the public to reduce electricity usage during peak hours and shift high-energy tasks, like laundry and dishwashing, to the day when solar power is at its peak.

As Cyprus braces for a difficult few days, authorities are calling on citizens to play their part in ensuring the stability of the island’s power grid.

Delayed Cyprus Fuel Terminal Adds €1.67 Million To 2026 Budget Allocation

A delay in completing Cyprus’ strategic petroleum-products terminal has shifted €1.67 million in expected payments into the 2026 budget, prompting a revised budget allocation for the state’s fuel-storage organization, CODAP. The project was completed on June 30, 2026, later than the December 2025 handover originally anticipated.

The change in timing has altered the project’s payment schedule, but it will not increase CODAP’s overall 2026 budget of €111.3 million. After contractual deductions for the delay, payments to the contractor are expected to total €48.2 million, compared with the original contract value of €51 million.

Why The Budget Is Being Revised

When CODAP prepared its 2026 budget in June 2025, it expected construction to finish by the end of that year. The organization therefore forecast that the main payments to the contractor would be made during 2025 and included lower construction funding in its 2026 budget.

But delays by the contractor pushed completion to June 30, 2026. As a result, payments that had been expected earlier must now be covered through a budget amendment. The revised allocation will be discussed by Parliament’s Finance Committee on Friday.

Of the €1.67 million adjustment, €1.27 million relates to the first half of the contractor’s retention payment, which is payable upon handover under the contract. The remaining half is due 24 months after delivery.

A further €250,000 is set aside for work that has not yet been certified. The contractor is expected to complete these non-critical items during 2026. Another €150,000 covers payments to the project’s engineering consultants, whose fees are linked to construction progress and completion.

Contractual Deductions Reduce The Final Cost

CODAP withheld €1.27 million from the contractor in 2025 because of the late delivery. The deduction represents the maximum penalty stipulated in the contract: 2.5% of the contract value, applied in response to the delay against the agreed construction period of 24 months.

After accounting for that deduction and the scheduled retention payment, the total amount expected to be paid to the contractor is €48.2 million—below the original €51 million contract price.

A Critical Part Of Cyprus’ Fuel Reserves

The terminal is located at the Vasilikos Energy Centre and has seven petroleum-product storage tanks. It holds most of Cyprus’ fuel reserves, which are intended to help protect the country against supply disruptions.

Countries are required to maintain fuel stocks equivalent to 90 days of consumption. Those reserves must remain available for release to the market if supply problems arise, making the terminal a key part of Cyprus’ energy-security infrastructure.

The Future Forbes Realty Global Properties
Aretilaw firm
Uol
eCredo

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter