Breaking news

Cyprus Explores Legal Recourse Following EU Demand for LNG Grant Refund

The Cypriot government is now assessing its strategic options after the European Commission issued a repayment demand. Energy Minister George Papanastasiou announced on Thursday that Cyprus must return €67.2 million from a total of €73 million allocated in grants for the Vasiliko liquefied natural gas terminal project. The minister clarified that funds amounting to €5.8 million, spent on activities predating the grant awards, remain unaffected by the demand.

EU Fund Repayment Demand

The repayment notice, issued by the European Climate, Infrastructure, and Environment Executive Agency (Cinea), follows earlier communications from the Commission. Initially, back in July of the previous year, the Commission had demanded repayment of the bulk of the funds, a figure that has been slightly reduced in the most recent correspondence. The stated demand cites possible irregularities during the evaluation phase of the tender process for the project, implicating several international consortium members including companies from the China Petroleum Pipeline Engineering Co and Metron Energy Applications SA.

Government Response and Legal Consultation

Following the latest letter from Cinea, the Cypriot government responded with a detailed submission that was ultimately dismissed, leading to the reiterated demand. Minister Papanastasiou emphasized that legal experts are now reviewing the issue, with consultations involving specialized English legal advisors expected shortly. The government is considering a range of appeals, which might include approaches to the European Ombudsman or bringing the matter before the Court of Justice of the European Union. Notably, despite any pending legal actions, the government is obligated to deposit the €67.2 million by November 6 and later seek reimbursement if their appeals succeed.

Project Challenges and Technical Concerns

The broader context of this development includes significant operational and technical issues at the Vasiliko LNG terminal project. Originally launched in 2019, the project has faced delays and technical complexities, notably with aspects of the floating storage and regasification unit (FSRU) Prometheas, currently undergoing certification in Malaysia. Questions over design and material standards have also surfaced, stalling progress at the project’s pier and contributing to prolonged delays.

Outlook and Future Implications

Despite the controversies, Minister Papanastasiou remains confident in the viability of the Vasiliko project, suggesting that once key assets such as the FSRU are operational, the remaining infrastructure can be completed to facilitate gasification and conventional power generation. The situation also underscores the broader challenges faced by governments managing EU-funded projects, particularly as rigorous compliance and oversight demand meticulous transparency and legal precision.

As Cyprus navigates these complex administrative and legal waters, the unfolding developments will have significant implications not only for national energy strategy but also for future engagements with EU funding mechanisms.

Cyprus Moves To Unlock More Solar Power With First Large-Scale Battery Storage Contracts

Cyprus is preparing to sign the first contracts for large-scale electricity storage batteries on Tuesday, a project expected to improve the grid’s ability to manage growing renewable energy production and reduce the curtailment of solar power.

A Long-Awaited Grid Fix

Energy Minister Michalis Damianos said the agreements will cover 120MW of centralised storage capacity that will be managed by the transmission system operator. The project, valued at €50 million, is expected to deliver the batteries in January 2027, with installation scheduled to take place over the following two to three months.

According to Damianos, the system should become operational by the summer of 2027, a period when both electricity demand and solar generation typically peak. He said the storage facilities will allow energy currently lost due to a lack of storage capacity to be retained and used when needed.

Why Storage Has Become Essential

The batteries are designed to absorb excess renewable electricity during periods of overproduction and release it back into the system when demand increases. Their introduction is expected to reduce the curtailments currently affecting solar generators and improve the use of renewable energy already being produced across the island.

Former Energy Minister George Papanastasiou told Sigma that planning for the project began in 2023 in cooperation with the European Commission. The objective was to address growing losses from renewable energy generation that the electricity network cannot currently absorb.

By the end of May 2026, approximately 160,000 megawatt hours of renewable energy had been lost through curtailments affecting residential photovoltaic systems, commercial solar parks, and wind installations. According to Papanastasiou, renewable electricity production exceeds demand during several hours of the day, leaving part of the output unable to be utilised.

The Cost Of Growing Faster Than The Grid

The challenge has become more pronounced as renewable generation capacity has expanded faster than the infrastructure required to manage surplus electricity. Data from the distribution system operator show that around 306 gigawatt hours of renewable energy were curtailed in 2025, compared with approximately 167 gigawatt hours a year earlier.

Papanastasiou acknowledged criticism that storage deployment has not kept pace with the growth of renewable energy projects, although he noted that regulatory and financing challenges slowed implementation. He added that the development of storage and generation capacity needs to progress in parallel, a challenge faced by many energy markets.

Private Capital Is Also Entering The Market

The state-backed battery installation forms part of a broader expansion of energy storage capacity across Cyprus. Alongside the project managed by the transmission system operator, the Electricity Authority of Cyprus (EAC) and private developers are advancing their own investments.

Current figures show 36 applications for battery storage projects with a combined requested capacity of approximately 925MW. The EAC has submitted applications for storage facilities in Dhekelia and Moni with a combined capacity of 180MW, while private-sector projects exceeding 150MW have progressed through various stages of the approval process.

Grid Stability Comes First

According to Papanastasiou, the state-owned battery system will primarily serve grid stability and energy security objectives rather than operate as a commercial trading asset. The facilities will store electricity during periods of surplus generation and release it when demand rises or when supply pressures emerge.

Privately operated storage projects could also contribute to the market by storing lower-cost renewable electricity and dispatching it later when demand and prices are higher.

As renewable energy continues to account for a larger share of Cyprus’ electricity mix, storage infrastructure is expected to play an increasingly important role in balancing supply and demand, reducing curtailments, and improving the overall efficiency of the power system.

eCredo
Aretilaw firm
Uol
The Future Forbes Realty Global Properties

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter