Cyprus’s Environmental Authority has conditionally approved a biological wastewater treatment plant for Salt, a residential development under construction in Asomatos, within the Kourion municipality. The decision clears a key issue for the project, developed by Abazalia Holdings Ltd, but does not grant retrospective approval for buildings erected without the required permits.
A €10 Million Residential Project
The development includes five apartment buildings with 84 units, alongside a gym, sauna, communal swimming pool and 170 parking spaces. The project has a total building area of 6,208 square metres and an estimated cost of €10 million. Completion is expected within 22 months of the final permits being secured.
Follow THE FUTURE on LinkedIn, Facebook, Instagram, X and Telegram
Solar panels are planned for the rooftops and are expected to provide at least 25% of the development’s energy needs.
Treatment And Reuse Of Wastewater
The proposed treatment plant will use membrane bioreactor technology, known as MBR, and will have capacity to process 37.5 cubic metres of wastewater a day—enough to serve an estimated 219 population equivalents.
Treated water is intended for irrigating landscaped areas and cleaning internal roads. Some will also be supplied to the local community free of charge. The plant is expected to produce about 18.5 kilograms of sludge daily, which will be held in a sealed tank and collected by licensed companies.
Environmental Sensitivity In The Area
The site’s location makes wastewater management particularly significant. The Akrotiri Ramsar-protected area lies about 500 metres to the southeast, while Akrotiri Salt Lake is approximately 1,200 metres away. The plot also falls within the Akrotiri nitrate-vulnerable zone, where the use of soakaways is prohibited.
Approval Does Not Resolve Permit Breaches
The approval comes against a backdrop of planning and environmental concerns. During the review, authorities found that construction of the apartment buildings had begun and advanced substantially without the required permits. The Department of Environment notified the Limassol District Local Government Organisation, stressing the need to enforce the law and halt the works.
An administrative fine was imposed on the development’s owner in October 2026 and, according to the information available, has been paid.
The Environmental Authority has stressed that its decision covers only the wastewater treatment plant. It does not retrospectively legalise buildings constructed without the necessary approvals.
Responsibility Rests With The Permitting Authority
In reaching its assessment, the Authority considered European Court of Justice case law and opinions issued by the Attorney General in 2011 and 2022. These set out that when a project proceeds without the required environmental assessment, authorities must consider how to address the resulting unlawful consequences and, subject to conditions, whether a retrospective environmental study is possible.
The Authority also clarified that responsibility for taking measures concerning projects already completed—or substantially advanced—without the required environmental assessment lies with the body responsible for issuing the planning or other relevant permit.