Opens in a new tab

Breaking news

Cyprus And Greece Outline Joint Tourism Plans For Summer 2026

Strategic Partnership Enhances Tourism Prospects

The Cyprus Tourism Authority (EOT Cyprus) presented proposals for summer 2026 focused on strengthening tourism cooperation between Cyprus and Greece, with joint efforts aimed at attracting visitors from long-haul markets.

Greece: The Top Destination For Cypriot Travelers

At an event on April 28, Athena Spakouri, Director of EOT Cyprus, said Greece is expected to remain the main travel destination for Cypriot residents, with plans extending beyond established locations to include lesser-known regions. This approach reflects a broader effort to diversify travel options while maintaining strong demand between the two countries.

Complementary Destinations, Unified Vision

Building on this, Spakouri noted that Cyprus and Greece offer complementary tourism experiences rather than competing directly. Joint programmes are therefore being positioned to attract visitors from markets such as the United States and China, while tourism activity continues to be assessed in the context of broader geopolitical developments.

Robust Air And Sea Connectivity

Supporting this cooperation, Konstantinos Kollias said around 600,000 Cypriots travelled to Greece in 2025. Frequent flights, short travel times, and ferry connections between Limassol and Piraeus continue to facilitate movement between the two countries and sustain travel flows.

Diverse Tourism Offerings for a New Era

Konstantinos Kollias highlighted that Greece’s tourism portfolio spans from traditional seaside holidays to sectors such as cultural, religious, gastronomic, agritourism, ecotourism, spa, conference, and medical tourism.

This range reflects the expansion of tourism offerings across different segments and travel preferences. In parallel, Joseph Iosif referred to Greece as a “second homeland” for Cypriot travellers, pointing to longstanding cultural and travel links between the two countries.

Innovative Programs And Strengthened Connections

Building on this approach, the EOT strategy includes initiatives focused on gastronomic routes, cultural trails, thematic and religious tourism, as well as curated city breaks in destinations such as Athens and Thessaloniki. These programmes were presented at the event alongside references to historical, cultural, and religious connections between Cyprus and Greece, including remarks from Bishop Gregorios of Mesaoria.

Boosting Air Connectivity And Island Accessibility

At the same time, airlines including Aegean Airlines, Sky Express, and Cyprus Airways outlined plans to expand connections between Cyprus and Greece, with a focus on increasing access to island destinations. The event also brought together stakeholders from the Deputy Ministry of Tourism, Hermes Airports, tour operators, and ACTAA, reflecting coordination across different parts of the tourism sector.

Limassol Port Electrification Awaits Grid Connection And EU Funding

Plans to equip Limassol port with shore-side electricity are advancing at the technical level, but unresolved administrative procedures, a pending grid connection and the need to secure European funding continue to delay implementation.

The proposed shore-power system, also known as cold ironing, would allow vessels to connect to electricity while berthed, reducing reliance on onboard engines and cutting emissions and noise in the surrounding area.

Technical Studies Near Completion

Transport Minister Evi Tsolaki said work is progressing through the EU-backed DecarbonLim programme, which is preparing the technical assessment and feasibility study required before construction can begin. The ministry is seeking regular updates from the Cyprus Ports Authority on the studies’ completion timetable.

The initiative also involves Frederick University, Eurogate Container Terminal Limassol, DP World Limassol, the Electricity Authority of Cyprus, the Cyprus Transmission System Operator and Limassol Municipality.

Grid Connection Remains A Key Hurdle

Despite progress on the studies, construction cannot proceed until the project secures a connection to the national transmission network.

Tsolaki said the ministry has requested land from the Department of Lands and Surveys for an electricity substation. Once the site is allocated, the relevant applications can be submitted to the Cyprus Transmission System Operator to advance the grid-connection process.

Until these steps are completed, the project will remain in the preparatory phase, even if the technical studies are finalised.

European Funding Adds Urgency

The feasibility work under DecarbonLim will support an application for construction financing, Tsolaki said. A competitive European funding call is currently open, and the ministry intends to submit an application within the required timeframe.

The funding window has raised concerns in parliament. MP Fotini Tsiridou warned that further delays could undermine Cyprus’ chances of securing EU support, noting that similar port electrification projects elsewhere in the bloc have already received funding.

Speaking to Entrepreneurial Limassol, published by the Limassol Chamber of Commerce and Industry, Tsiridou said she had observed some progress but had yet to receive a formal response to her parliamentary question.

Environmental And Commercial Benefits

Tsiridou argued that shore-side electricity would deliver benefits beyond emissions reductions, including less noise and air pollution for residents near the port.

“Our port should not be disconnected from the rest of the city,” she said, describing shore-power infrastructure as both a necessity and a European obligation.

Across Europe, port electrification is increasingly linked to environmental performance and competitiveness. By allowing compatible vessels to switch off auxiliary engines while docked, shore-power systems can reduce local emissions and noise while supporting wider decarbonisation goals.

Construction Timetable Still Unclear

The Cyprus Ports Authority signed a contract with DBA S.p.A. in July 2025 for a comprehensive study of the system’s technical, economic and environmental requirements. The work was intended to establish the basis for installation and identify any necessary port infrastructure upgrades.

More than a year later, key steps concerning land allocation, grid connection and financing remain unresolved. No timetable has been announced for completing these procedures or submitting the final funding application.

Limassol’s shore-power project therefore remains between planning and implementation. Its next milestones are securing the substation site, progressing the transmission-network application and obtaining construction financing. Until these are in place, the port’s transition to shore-side electricity cannot move into the construction phase.