Opens in a new tab

Breaking news

FSRU Transformation: Promitheas Nears Critical Integration Milestone

The integration of essential systems on the vessel Promitheas is on track for completion by late November or early December. This pivotal phase will usher the ship into a terminal for its certification as a Floating Storage and Regasification Unit (FSRU), marking a significant milestone in LNG infrastructure development.

Timed Precision Amid Supply Chain Delays

Georgios Asiikalis, President of the Gas Infrastructure Company (ETYFA), highlighted that all necessary components are pre-positioned on the vessel, awaiting installation. He noted that delays stemmed primarily from the absence of ready-made parts, which required additional time for manufacture and delivery. With components now onboard, operations are advancing into the installation phase.

Terminal Certification And Strategic Decisions

Asiikalis emphasized that the final terminal designation for Promitheas will depend on the findings of an upcoming gap analysis related to the Vasiliko terminal. The project coordinator will complete and submit this analysis on December 19, dictating whether the vessel will be certified at the local terminal or potentially at an international facility.

Ensuring Operational Integrity

The certification process is critical to verifying that the vessel can maintain LNG at minus 160 degrees Celsius without any vapor loss. Concurrent consultations are underway to determine the development timeline of the Vasiliko terminal. Should the terminal’s construction conclude promptly, Promitheas will transition there; otherwise, an alternative certification site will be sought.

A Pivotal Investment In Energy Infrastructure

President Asiikalis reiterated the importance of these milestones, noting that the successful conversion of Promitheas signifies not only enhanced operational capabilities but also safeguards an investment valued at 200 million euros. In this context, the vessel is not merely a component of the system but represents its operational centerpiece.

Limassol Port Electrification Awaits Grid Connection And EU Funding

Plans to equip Limassol port with shore-side electricity are advancing at the technical level, but unresolved administrative procedures, a pending grid connection and the need to secure European funding continue to delay implementation.

The proposed shore-power system, also known as cold ironing, would allow vessels to connect to electricity while berthed, reducing reliance on onboard engines and cutting emissions and noise in the surrounding area.

Technical Studies Near Completion

Transport Minister Evi Tsolaki said work is progressing through the EU-backed DecarbonLim programme, which is preparing the technical assessment and feasibility study required before construction can begin. The ministry is seeking regular updates from the Cyprus Ports Authority on the studies’ completion timetable.

The initiative also involves Frederick University, Eurogate Container Terminal Limassol, DP World Limassol, the Electricity Authority of Cyprus, the Cyprus Transmission System Operator and Limassol Municipality.

Grid Connection Remains A Key Hurdle

Despite progress on the studies, construction cannot proceed until the project secures a connection to the national transmission network.

Tsolaki said the ministry has requested land from the Department of Lands and Surveys for an electricity substation. Once the site is allocated, the relevant applications can be submitted to the Cyprus Transmission System Operator to advance the grid-connection process.

Until these steps are completed, the project will remain in the preparatory phase, even if the technical studies are finalised.

European Funding Adds Urgency

The feasibility work under DecarbonLim will support an application for construction financing, Tsolaki said. A competitive European funding call is currently open, and the ministry intends to submit an application within the required timeframe.

The funding window has raised concerns in parliament. MP Fotini Tsiridou warned that further delays could undermine Cyprus’ chances of securing EU support, noting that similar port electrification projects elsewhere in the bloc have already received funding.

Speaking to Entrepreneurial Limassol, published by the Limassol Chamber of Commerce and Industry, Tsiridou said she had observed some progress but had yet to receive a formal response to her parliamentary question.

Environmental And Commercial Benefits

Tsiridou argued that shore-side electricity would deliver benefits beyond emissions reductions, including less noise and air pollution for residents near the port.

“Our port should not be disconnected from the rest of the city,” she said, describing shore-power infrastructure as both a necessity and a European obligation.

Across Europe, port electrification is increasingly linked to environmental performance and competitiveness. By allowing compatible vessels to switch off auxiliary engines while docked, shore-power systems can reduce local emissions and noise while supporting wider decarbonisation goals.

Construction Timetable Still Unclear

The Cyprus Ports Authority signed a contract with DBA S.p.A. in July 2025 for a comprehensive study of the system’s technical, economic and environmental requirements. The work was intended to establish the basis for installation and identify any necessary port infrastructure upgrades.

More than a year later, key steps concerning land allocation, grid connection and financing remain unresolved. No timetable has been announced for completing these procedures or submitting the final funding application.

Limassol’s shore-power project therefore remains between planning and implementation. Its next milestones are securing the substation site, progressing the transmission-network application and obtaining construction financing. Until these are in place, the port’s transition to shore-side electricity cannot move into the construction phase.

eCredo
The Future Forbes Realty Global Properties
Aretilaw firm
Uol

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter