Delay And Legal Strife Derail Paphos–Polis Chrisochous Road Project

A year after the termination of the initial contract, not a single meter of the Paphos–Polis Chrisochous road has been constructed. Compounding the delays, the feasibility study for the project now faces significant legal entanglements that threaten to derail its overall timeline.

Contract Termination And Emerging Legal Battles

The project hit an early setback when the Ministry of Public Works terminated the contract with the company AktoR on November 11, 2024, due to non-fulfillment of contractual obligations. Despite the ministry’s subsequent efforts to re-initiate the bidding process, AktoR challenged the revised terms published in the Official Gazette on August 8, 2025. The company contended that the new conditions detracted from the fundamental principles of administrative law, specifically citing concerns over transparency, equal treatment, and fair competition.

Revised Schedules And Continued Delays

Originally, the adjusted schedule placed the submission deadline for bids on November 7, 2025. However, after legal interventions and a series of appeals, the Ministry of Public Works sought approval from the Review Authority to postpone the deadline to February 6, 2026. This change was rationalized by the need to avoid the necessity of a complete re-announcement, a situation that could trigger further delays. In addition, the timeline for submitting and clarifying questions by economic operators was extended significantly, underscoring the complexity of the procurement process.

Temporary Measures And Their Implications

In a bid to safeguard its interests, AktoR successfully obtained temporary measures that halted the acceptance of bids. The company’s legal argument, favoring the modification or supplementation of the tender terms, aimed to ensure compliance with established public procurement norms. Even though the Ministry of Public Works presented its case by highlighting the negative consequences that might arise from issuing such measures, it was left to the Review Authority’s judgment to decide the outcome. A hearing was set for November 3, 2025, with a decision expected by the end of November or early December, promising to minimize further delay.

Looking Ahead: A Stalled Construction Timeline

Despite attempts to expedite the project and commence construction promptly, the procedural complications have pushed the final bid submission date to February 6, 2026, marking a substantial postponement from the initial termination in November 2024. As debates continue and the Review Authority’s decision looms, stakeholders remain on edge, awaiting clarity on a project that is pivotal for the region’s infrastructure development.

The unfolding situation illustrates the persistent challenges in managing large-scale public infrastructure projects, where legal, administrative, and commercial interests often intersect, leading to significant delays and operational uncertainty.

Central Bank Of Cyprus Balance Sheet Reflects Strong Eurosystem Position

Overview Of Financial Stability

The Central Bank of Cyprus (CBC) has released its latest balance sheet, reaffirming its steadfast role within the Eurosystem. The balance sheet, featuring total assets and liabilities of €29.545 billion, underscores the institution’s stable financial posture at the close of January 2026.

Asset Allocation And Strategic Holdings

Governor Christodoulos Patsalides issued the balance sheet, which details the CBC’s asset composition under the Eurosystem framework. Notably, the bank’s gold and gold receivables amounted to €1.635 billion, providing a significant hedge and stability to its balance sheet. Additional asset categories include claims on non-euro area residents denominated in foreign currency at €1.099 billion, while claims on euro area residents in both foreign and domestic currency add further depth to its portfolio.

The most substantial asset category, intra-Eurosystem claims, reached €19.438 billion, an indication of the CBC’s deep integration with its European counterparts. Furthermore, euro-denominated securities held by euro area residents contributed €6.587 billion. Despite a marked emphasis on these areas, lending to euro area credit institutions in monetary policy operations recorded no activity during the period.

Liability Structure And Monetary Policy Implications

On the liabilities side, banknotes in circulation contributed €3.218 billion. Liabilities to euro area credit institutions associated with monetary policy operations were notably the largest single category, totaling €17.636 billion. Supplementary liabilities included those to other euro area residents, which aggregated to €4.989 billion, with government liabilities playing a predominant role at €4.754 billion.

Other liability items, such as claims related to special drawing rights allocated by the International Monetary Fund at €494.193 million, and provisions of €596.571 million, further articulate the CBC’s exposure. Revaluation accounts stood at €1.643 billion, and overall capital and reserves were confirmed at €333.822 million, completing the picture of a well-capitalized institution.

Conclusive Insights And Strategic Alignment

The detailed breakdown illustrates the CBC’s sizeable intra-Eurosystem exposures, reinforcing its central role within Europe’s monetary landscape. With an asset-liability balance maintained at €29.545 billion, the CBC’s financial position remains robust, indicating a commitment to structural stability and strategic risk management.

This fiscal disclosure not only provides transparency into the CBC’s operations but also serves as a benchmark for comparative analysis among other central banks within the Eurosystem, highlighting the intricate balance between asset liquidity, regulatory oversight, and monetary policy imperatives.

The Future Forbes Realty Global Properties
eCredo
Uol
Aretilaw firm

Become a Speaker

Become a Speaker

Become a Partner

Subscribe for our weekly newsletter